1976: The Pingtan Wind Power Test Station is set up in Pingtan county, Fujian province, followed by the establishment of test stations on Shengsi Island, Zhejiang province, and Badaling in Beijing in 1979.

May 1986: China's first grid-connected demonstration wind farm, boasting three 55-kilowatt wind turbine generators from Denmark, is built in Malan Bay, Rongcheng, Shandong province.

1986 to 1992: A China-Sweden wind energy science and technology cooperation project is rolled out in China. The two sides jointly carry out research on wind turbine stability and flows around blades. The research proves essential to designing and testing wind turbines in China.

1996: The now-defunct State Economic and Trade Commission launches the Investment and Reform Program to select the best-performing enterprises over a three-year period. Selected companies are given access to low-interest preferential loans to widen the wind power market.

March 1996: The now-defunct State Planning Commission launches the Ride the Wind Program. The government provides 240-megawatt wind farm development opportunities to attract foreign companies to the Chinese market through joint ventures.

1997: The Institute of Measurement and Control of Rotating Machinery and Wind Energy Devices is jointly established by the Northwestern Polytechnical University and the Berlin Polytechnic University.

June 1998: The first wind-driven generator made in China is linked to the grid in the Xinjiang Uygur autonomous region. The localization rate of its components is 33.4 percent.

2002 and 2005: The Sino-German wind power talent training cooperation project organizes two rounds of training, the 32 participants make up the initial core of China's wind industry leadership.

2003: The State Planning Commission launches the Concession Bidding Program, requiring minimum local component rates for wind turbine manufacturing. The required local components in wind turbines is fixed at no less than 50 percent in the first round in 2003. The proportion climbs to 75 percent in 2007 and 2008.

June 2006: GE Energy's first wind turbine assembly plant in China is established in Shenyang, capital of Liaoning province.

Sept 2006: The first wind power plant funded by Gamesa, Spain's largest wind power equipment manufacturer, is put into operation in Tianjin.

2006 to 2012: The National Science and Technology Infrastructure Program undertakes six projects to support wind energy development and utilization.

2007 to 2014: The National Basic Research Program of China carries out four projects to support the R&D and manufacturing of large wind turbines.

2009 to 2014: The National High Technology Research and Development Program launches eight projects to support wind energy development and utilization, and develop knowledge and R&D to advance local manufacturing of state-of-the-art equipment.

Nov 2010: The National Standards Committee approves the Rules and Procedures for Conformity Testing and Certification of Wind Turbine Generator Systems, which pave the way for the Chinese certification system to become recognized internationally.

2010: The Ministry of Science and Technology approves the establishment of the National Key Laboratory of Wind Power Generation System.

2016 and 2018: A national center of quality supervision and inspection for wind power equipment is officially established in Gansu and Jiangsu provinces.

Feb 2022: A 13-MW offshore wind turbine rolls off the production line in Fujian province. The localization rate of components for the turbine, which has the largest single-unit capacity in Asia at the time, reaches 90 percent.

July: A 16-MW offshore wind turbine is assembled in Fujian, the biggest in the world in terms of single-unit capacity. All of its key components are made in China.

Top
BACK TO THE TOP
English
Copyright 1995 - . All rights reserved. The content (including but not limited to text, photo, multimedia information, etc) published in this site belongs to China Daily Information Co (CDIC). Without written authorization from CDIC, such content shall not be republished or used in any form. Note: Browsers with 1024*768 or higher resolution are suggested for this site.
License for publishing multimedia online 0108263

Registration Number: 130349
FOLLOW US
 
主站蜘蛛池模板: 成人免费午夜性视频 | 最爽的乱淫片免费 | 免费人成网ww44kk44 | 免费网站www7788con | 亚洲第一页在线播放 | 全黄一级裸片视频在线观看 | 999久久久精品视频在线观看 | 中文字幕成人乱码在线电影 | 国产区成人精品视频 | 国产婷婷一区二区在线观看 | 水蜜桃爱爱yy视频在线观看 | 国产51| 欧美福利片在线观看 | 免费看欧美一级特黄a毛片 免费看欧美一级特黄α大片 | 日批视频网址免费观看 | 成人深夜网站 | 精品国产品欧美日产在线 | 久久天天躁狠狠躁夜夜中文字幕 | 美国一级毛片免费 | 一级视频免费观看 | 日本特黄特色大片免费视频高清 | 伊人久久中文字幕 | 青草草在线观看 | 妖精视频在线观看网站 | a级黄色免费 | 国产高清看片日韩欧美久久 | 97一区二区三区四区久久 | 天天综合色 | 欧洲精品在线观看 | 青青热久免费精品视频精品 | 欧美一级毛片片免费 | 久久免费国产精品一区二区 | 欧美成人精品第一区 | 大陆一级黄色片 | 一级特黄色大片 | 国产在线每日更新 | 国产成人欧美一区二区三区的 | 国产一区在线播放 | 精品国产999 | 色一情一区二区三区四区 | 欧美一级毛片做受 |